Himachal Pradesh’s four planned industrial parks are proposals, not approved projects. The state has sent two to the Centre under the BHAVYA scheme: Manjholi in Nalagarh (150 acres, ₹154 crore) and Beetan in Una (75 acres, ₹80 crore). Kadrori in Kangra and Kandaghat in Solan are still being prepared. BHAVYA pays for park infrastructure, not for factories, so the opening for entrepreneurs lies in supplying the units that will settle around the parks: packaging, intermediates, testing and storage.(Himachal Pradesh Industrial Parks)
7 November 2026, after Amar Ujala reported on 5 November that project reports for two parks are with the Centre. Next milestone: first-phase selection under BHAVYA, with approval signals reported for December 2027.
Confirmed so far: the Union Cabinet approved BHAVYA on 18 March 2026 (100 parks, ₹33,660 crore, up to ₹1 crore per acre); the state says it has submitted proposals for Manjholi and Beetan; Himachal is in the 25-acre minimum group for hilly states. Still awaited: selection of any Himachal park; area and cost for Kadrori and Kandaghat; plot prices, sector mix and allotment rules; the state’s new industrial policy, reported on 28 October as set for the next Cabinet meeting. (Himachal Pradesh Industrial Parks)
Which Himachal Pradesh industrial parks are in the BHAVYA pipeline?
Two of the four parks have papers with the Centre; the other two have no area or cost yet. The cost figures below are the state’s own numbers.
| Park | District | Area | Estimated cost | Status |
| Manjholi (Nalagarh) | Solan | 150 acres | ₹154.39 crore | Proposal submitted |
| Beetan | Una | 75 acres | ₹80 crore | Proposal submitted |
| Kadrori | Kangra | Not fixed | Not fixed | Proposal being prepared |
| Kandaghat | Solan | Not fixed | Not fixed | Proposal being prepared |
PTI quoted the state as saying Beetan lies close to the upcoming Bulk Drug Park at Haroli and is meant to support it. Amar Ujala reports about 30,000 jobs across the four parks.
What does BHAVYA fund, and how will park plots be allotted?
BHAVYA pays for the park, and any incentive for a factory sits with the state.
| Support | Authority | What it covers | Conditions | Status |
| BHAVYA central assistance | DPIIT, through NICDIT | Up to ₹1 crore per acre for roads, underground utilities, treatment plants, ready-built sheds, testing labs, warehousing and worker housing | Equity in the park’s special purpose company, tied to land value, released in three tranches (40:40:20) against milestones | Cabinet-approved; no Himachal park selected |
| Incentives for units | Himachal Industries Department | Set by the state’s new industrial policy | Per that policy | Awaited |
Under DPIIT’s guidelines, each approved park is run by a special purpose company that allots and leases plots to units in a transparent, non-discriminatory way. A private developer can join as anchor investor and take up to 25% of the land, if it builds a unit of at least ₹10 crore in a hilly state. The second funding tranche needs land allotted to at least two manufacturing units with investment commitments, and development work gets 24 months after approval. This suggests ready plots are some years away. (Himachal Pradesh Industrial Parks)
Our BHAVYA scheme guide covers the developer side.
Which businesses do Himachal’s industrial parks open up?
| Opportunity | Why this news helps it | Likely scale | Who it suits | What to check first |
| Pharma secondary packaging (cartons, labels, leaflets) | Manjholi sits in the Nalagarh belt, part of the Baddi-Barotiwala-Nalagarh corridor, which the state says has more than 2,500 industrial enterprises | Micro to small | Printers and carton units near Baddi and Nalagarh | Vendor-approval steps at three local buyers |
| Intermediates and excipients for the bulk drug park | Beetan is planned beside Haroli, where Parliament heard in July 2026 that about 20% of Phase-I site work is done | Small to medium | Chemical graduates and existing chemical units; see API manufacturing | Effluent route: the park’s ₹273 crore treatment plant is at tender stage |
| Ready-built sheds, built-to-suit units and worker housing | BHAVYA funds these and lets private developers join the park company | Medium to large | Developers with net worth of at least 15% of project cost and a completed park of 50 acres | Land contribution and equity share |
| Testing and quality-control laboratories | The guidelines list testing labs as fundable and score them in park proposals | Small to medium | Analytical chemists and accredited-lab operators | Sample volume from nearby units |
| Warehousing and freight | BHAVYA funds warehousing; the Chief Minister has asked the Centre to extend the Baddi-Nalagarh rail line | Small to medium | Transport and storage operators in Solan and Una | Road-freight plan; rail is a request, not a sanction |
For a first-time investor with a modest budget, the stronger opening is a packaging or supplier unit in an existing Nalagarh or Una industrial area, because a park plot may be years away. (Himachal Pradesh Industrial Parks)
What should you check before investing near the Himachal parks?
- Product and buyer. Pick the product from a buyer’s purchase list, since no sector mix has been announced.
- Do not pay for a plot that does not exist yet; existing areas allot plots only where land is available.
- Power and water. The allotment form asks for connected load in kW and water in kilolitres, so size both early.
- Chemical and pharma units need a confirmed disposal route before they sign anything.
- Approvals and incentives. Proposals above ₹10 crore go to the state single-window authority, and unit incentives wait on the new policy, so keep subsidy out of your base case.
- Model road transport; the rail extension is only a request.
What can you use while the Himachal parks wait?
Two state routes are live today.
| Route | Who it suits | What it gives | Where to apply | Status |
| Plot or shed in an existing industrial area or estate | Units that need land now | Allotment by the Department of Industries | Application form (Annexure A-1), after consulting the General Manager of the District Industries Centre | Open where land is available |
| State single window | New units and expansions | One Common Application Form for clearances; proposals above ₹10 crore go to the State Single Window Clearance and Monitoring Authority | State single-window portal under the 2018 Act | In force |
What to prepare now and where to watch
- A project report with plant cost, power load and water need, because the allotment form asks for all three.
- Your MSME registration number, or the Directorate’s approval reference for medium and large projects.
- A means-of-finance split (promoter’s equity, loan, subsidy) and a bank conversation; our PMEGP guide covers one route for micro units.
- Earnest money by bank draft, which the form lists.
The next update will appear on the BHAVYA portal run by NICDC, on DPIIT’s scheme page and in the Himachal Industries Department’s announcements. Amar Ujala’s 5 November report is the latest on the project reports.(Himachal Pradesh Industrial Parks)
Planning a Manufacturing unit near the Himachal parks?
A project report for this kind of unit sets out plant cost, machinery, raw material, power load and profitability in the format banks and government programmes ask for. It can support a plot application or a bank discussion, though it cannot promise approval, subsidy or a loan. Entrepreneur India’s publisher, NPCS, prepares such reports.