PROJECT DESCRIPTION

The most commonly used cement in the world is Portland cement, which is formed at high temperatures that chemically combine the ingredients into new components, including calcium silicates and calcium aluminates. When the cement clinkers are ground with approximately 5% gypsum, they form Portland cement. These compounds allow cement to set when combined with water and to form strong bonds that can withstand pressure, water immersion, and other elements. In the manufacture of Portland cement, clinker is lumps or nodules, usually 3-25 mm in diameter, produced by sintering limestone and alumino-silicate during the cement kiln stage. Cement clinkers are formed by the heat processing of cement elements in a kiln. Limestone, clay, bauxite, and iron ore sand in specific proportions are heated in a rotating kiln at 2,770° Fahrenheit (1,400° Celsius) until they begin to form cinder lumps, which are also known as cement clinkers. Cement clinkers are usually ground with gypsum to produce the fine powder later mixed with liquid to produce cement, although some manufacturers ship cement clinkers in their lump form to cut down on dust. Cement is heavily relied upon to produce mortar, grouts, and concrete, and cement clinkers are the first stage, post firing, in making cement. Cement has strong bonding qualities when mixed with gypsum and water to form a hydration reaction, and it forms approximately one tenth of concrete, mixed with rocks, sand, and other materials and used in building construction all over the world. Concretes high versatility makes it an ideal tool for building projects of all shapes and sizes, from skyscrapers to pool sides. Concrete can also be recycled when it has outlived its usefulness and converted back into cement clinkers through careful processing. Clinker is ground (usually with the addition of a little gypsum, that is, calcium sulfate dehydrate) to become Portland cement. It may also be combined with other active ingredients or chemical admixtures to produce: ground granulated blast furnace slag cement, pozzolana cement & silica fume cement. The cement industry is one of the main beneficiaries of the infrastructure boom. With robust demand and adequate supply, the industry has bright future. The Indian Cement Industry with total capacity of 165 million tones is the second largest after China. Cement industry is dominated by 20 companies who account for over 70% of the market. Individually no company accounts for over 12% of the market. The major players like L&T and ACC have been quiet successful in narrowing the gap between demand and supply. Private housing sector is the major consumer of cement (53%) followed by the government infrastructure sector. Similarly northern and southern region consume around 20%-30% cement while the central and western region are consuming only 18%-16%. India is the 2nd largest cement producer in world after china. Right from laying concrete bricks of economy to waving fly overs cement industry has shown and shows a great future. Domestic demand for cement has been increasing at a fast pace in India. Cement industry has contributed around 8% to the economic development of India. Outsiders (foreign players) eyeing India as a major market to invest in the form of either merger or FDI (Foreign Direct Investment). Cement industry has a long way to go as Indian economy is poised to grow because of being on verge of development. The company continues to emphasize on reduction of costs through enhanced productivity, reduction in energy costs and logistics expenses. The cement sector is expected to witness growth in line with the economic growth because of the strong co-relation with GDP. Future drivers of cement demand growth in India would be the road and housing projects. As per the Working Group report on Cement Industry for the formulation of the 11th Plan, the cement demand is likely to grow at 11.5 per cent per annum during the 11th Plan and cement production and capacity by the end of the 11th Plan are estimated to be 269 million tones and 298 million tones, respectively, with capacity utilization of 90 per cent. There is a very good scope in this sector and new entrepreneurs should venture into this field. Few Indian Major Players are as under: ACC Ltd. Almora Magnesite Ltd. Ambuja Cement Eastern Ltd. Ambuja Cement Rajasthan Ltd. Barak Valley Cements Ltd. Bhilai Jaypee Cement Ltd. Binani Cement Ltd. Birla Corporation Ltd. Cement Manufacturing Co. Ltd. Century Textiles & Inds. Ltd. Chettinad Cement Corpn. Ltd. Deccan Cements Ltd. Dhar Cement Ltd. Greygold Cements Ltd. Gujarat High Tech Inds. Ltd. Gujarat Sidhee Cement Ltd. Heidelberg Cement India Ltd. Hemadri Cements Ltd. India Cements Ltd. Keerthi Industries Ltd. Lafarge India Pvt. Ltd. Lemos Cements Ltd. Malabar Cements Ltd. Mangalam Cement Ltd. Meghalaya Cement Ltd. My Home Inds. Ltd. N C L Industries Ltd. Namo Cements Ltd. Narmada Cement Co. Ltd. Penna Cement Inds. Ltd. Rain Commodities Ltd. Ramco Industries Ltd. Rishi Cement Co. Ltd. Sagar Cements Ltd. Sainik Finance & Inds. Ltd. Sanghi Industries Ltd. Saurashtra Cement Ltd. Shaktiman Cements Ltd. Shiva Cement Ltd. Shree Digvijay Cement Co. Ltd. Shri Hariganga Cement Ltd. Snhehadhara Industries Ltd. Sorabh Cement Ltd. Sparta Cements & Infra Ltd. Sri Vishnu Cement Ltd. Srichakra Cements Ltd. Sudarshan Cement & Multiprojects Ltd. Tata Chemicals Ltd. Ultratech Cement Ltd. Vinay Cements Ltd. Virgo Cements Ltd. Visaka Cement Industry Ltd. Zuari Cement Ltd.
Plant capacity Plant & machinery Working capital Cost of Project T.C.I Return Break even
75000 MT/Annum 433 Lakhs - 72700000 Cost of Project : 727 Lakhs 43.00 58.00

PROJECT AT A GLANCE

COST OF PROJECT MEANS OF FINANCE
Particulars Existing Proposed Total Particulars Existing Proposed Total
Land & Site Development Exp. ********** ********** ********** Capital ********** ********** **********
Buildings ********** ********** ********** Share Premium ********** ********** **********
Plant & Machineries ********** ********** ********** Other Type Share Capital ********** ********** **********
Motor Vehicles ********** ********** ********** Reserves & Surplus ********** ********** **********
Office Automation Equipments ********** ********** ********** Cash Subsidy ********** ********** **********
Technical Knowhow Fees & Exp. ********** ********** ********** Internal Cash Accruals ********** ********** **********
Franchise & Other Deposits ********** ********** ********** Long/Medium Term Borrowings ********** ********** **********
Preliminary& Pre-operative Exp ********** ********** ********** Debentures / Bonds ********** ********** **********
Provision for Contingencies ********** ********** ********** Unsecured Loans/Deposits ********** ********** **********
Margin Money - Working Capital ********** ********** ********** ********** ********** **********
TOTAL ********** ********** ********** TOTAL ********** ********** **********

COST OF PROJECT

Particulars Existing Proposed Total
COST OF PROJECT
Land & Site Development Exp.
Land Area Required ********** ********** **********
Land Development Cost, Boundary Wall, Gate & Road etc. ********** ********** **********
********** ********** **********
Buildings ********** ********** **********
Factory Building - ********** ********** **********
Office Buildings ********** ********** **********
********** ********** **********
Plant & Machineries ********** ********** **********
Indigenous Machineries ********** ********** **********
Erection & Installation ********** ********** **********
Laboratory Equipments ********** ********** **********
Miscellaneous Equipments like pumps, valves, pipeline & fittings ********** ********** **********
Imported Machineries ********** ********** **********
Technical know how ********** ********** **********
********** ********** **********
Office Vehicles ********** ********** **********
Office Automation Equipments (Telephone/ Fax/ Computer) ********** ********** **********
Office Equipment, Furniture plus Other Equipment & Accessories ********** ********** **********
Other Misc. Assets ********** ********** **********
Pre-operative & Preliminary Expenses ********** ********** **********
Provision for Contingencies ********** ********** **********
********** ********** **********
Total Capital Cost of Project ********** ********** **********
Margin Money for Working Capital ********** ********** **********
Total Cost of Project ********** ********** **********

PROFITABILITY AND NET CASH ACCRUALS

Particulars Operating Years
1-2 2-3 3-4 4-5 5-6
********** ********** ********** ********** **********
Revenue/Income/Realisation ********** ********** ********** ********** **********
Gross Sales Realisation ********** ********** ********** ********** **********
Less : Excise Duties/Levies ********** ********** ********** ********** **********
Net Sales Realisation ********** ********** ********** ********** **********
Total Revenue/Income/Realisation ********** ********** ********** ********** **********
********** ********** ********** ********** **********
Expenses/Cost of Products/Services/Items ********** ********** ********** ********** **********
Raw Material Cost ********** ********** ********** ********** **********
Indigenous ********** ********** ********** ********** **********
Total Nett Consumption ********** ********** ********** ********** **********
Lab & ETP Chemical Cost ********** ********** ********** ********** **********
Packing Material Cost ********** ********** ********** ********** **********
Sub Total of Net Consumption ********** ********** ********** ********** **********
Miscellaneous Cost ********** ********** ********** ********** **********
Employees Expenses ********** ********** ********** ********** **********
Fuel Expenses ********** ********** ********** ********** **********
Power/Electricity Expenses ********** ********** ********** ********** **********
Depreciation ********** ********** ********** ********** **********
Royalty & Other Charges ********** ********** ********** ********** **********
Repairs & Maintenance Exp. ********** ********** ********** ********** **********
Other Mfg. Expenses ********** ********** ********** ********** **********
Cost of Output of Goods Sold ********** ********** ********** ********** **********
********** ********** ********** ********** **********
Gross Profit ********** ********** ********** ********** **********
Administration Expenses ********** ********** ********** ********** **********
Technical Knowhow Fees & Exp. ********** ********** ********** ********** **********
Financial Charges ********** ********** ********** ********** **********
Long/Medium Term Borrowing ********** ********** ********** ********** **********
On Wkg. Capital Borrowings ********** ********** ********** ********** **********
Total Financial Charges ********** ********** ********** ********** **********
Selling Expenses ********** ********** ********** ********** **********
Total Cost of Sales ********** ********** ********** ********** **********
********** ********** ********** ********** **********
Net Profit Before Taxes ********** ********** ********** ********** **********
Tax on Profit ********** ********** ********** ********** **********
Net Profit After Taxes ********** ********** ********** ********** **********
Depreciation Added Back ********** ********** ********** ********** **********
Technical Knowhow Fees & Exp. ********** ********** ********** ********** **********
Net Cash Accruals ********** ********** ********** ********** **********

ASSSESSEMENT OF WORKING CAPITAL REQUIREMENTS

Particulars Stk.Prd. Stk.Prd. Operating Years
1st Year 2nd Yr&+ 1-2 2-3 3-4 4-5 5-6
Capacity Months Months % ********** ********** ********** ********** **********
CURRENT ASSETS ********** ********** ********** ********** **********
Stocks on Hand ********** ********** ********** ********** **********
Raw Material Cost ********** ********** ********** ********** **********
Indigenous ********** ********** M ********** ********** ********** ********** **********
Lab & ETP Chemical ********** ********** M ********** ********** ********** ********** **********
Packing Material ********** ********** M ********** ********** ********** ********** **********
Consumable Store ********** ********** M ********** ********** ********** ********** **********
Work-in-Process ********** ********** D ********** ********** ********** ********** **********
Finished Goods ********** ********** M ********** ********** ********** ********** **********
Current Expenses ********** ********** M ********** ********** ********** ********** **********
Receivables ********** ********** M ********** ********** ********** ********** **********
********** ********** ********** ********** ********** ********** **********
Total ********** ********** ********** ********** **********
Cash/Bank Balances ********** ********** ********** ********** **********
Gross Wkg. Capital ********** ********** ********** ********** **********
********** ********** ********** ********** **********

PROFITABILITY RATIOS, DSCR, DEBT EQUITY

Particulars Operating Years
1-2 2-3 3-4 4-5 5-6
Profit Percentages to Net Sales
Gross Profit ********** ********** ********** ********** **********
% Of G.P. to Net Sales ********** ********** ********** ********** **********
Net Profit Before Taxes ********** ********** ********** ********** **********
% of N.P.B.T. To Net Sales ********** ********** ********** ********** **********
Net Profit After Taxes ********** ********** ********** ********** **********
% of N.P.A.T. To Net Sales ********** ********** ********** ********** **********
Debt Service Coverage Ratio
Funds Available to Service Debts
Net Profit After Taxes ********** ********** ********** ********** **********
Depreciation Charges ********** ********** ********** ********** **********
Technical Knowhow Fees & Exp ********** ********** ********** ********** **********
Interest on Long/Medium Term ********** ********** ********** ********** **********
T o t a l ********** ********** ********** ********** **********
Debt Service Obligations
Repayment of Long/Medium Ter ********** ********** ********** ********** **********
Interest on Long/Medium Term ********** ********** ********** ********** **********
T o t a l ********** ********** ********** ********** **********
********** ********** ********** ********** **********
D. S. C. R. (Individual) ********** ********** ********** ********** **********
D. S. C. R. (Cumulative) ..... ********** ********** ********** ********** **********
D. S. C. R. (Overall) ........ ********** ********** ********** ********** **********
Parameters
Initial Equity Capital ********** ********** ********** ********** ********** **********
Credit Balance in P & L ********** ********** ********** ********** ********** **********
Total Capital excl Unsec Deposits ********** ********** ********** ********** ********** **********
Unsecured Dep. ********** ********** ********** ********** ********** **********
Total Equity incl Unsecured Deposits ********** ********** ********** ********** ********** **********
Long/Medium Term Borrowings from Bank ********** ********** ********** ********** ********** **********
Term lia. Incl Unsecured Deposit ********** ********** ********** ********** ********** **********
Total Liabilities ********** ********** ********** ********** ********** **********
Total Liabilities incl Unsecured Deposits ********** ********** ********** ********** ********** **********
DEBT EQUITY RATIO considering
i.e.Total Term Lia./NW
Unsecured Dep. as Equity ********** ********** ********** ********** ********** **********
Unsecured Dep. as Debt ********** ********** ********** ********** ********** **********
Total Outside Lia./NW ********** ********** ********** ********** **********
Assets Turnover Ratio (x) ********** ********** ********** ********** **********
No. of Shares of 10.00 each ********** ********** ********** ********** **********
Earnings Per Share (EPS) (in `) ********** ********** ********** ********** **********
Proposed divident ********** ********** ********** ********** **********
Cash EPS (in `) ********** ********** ********** ********** **********
Dividend Per Share(DPS) (in `) ********** ********** ********** ********** **********
Payout Ratio (%Age) ********** ********** ********** ********** **********
Retained Earnings/Share (in `) ********** ********** ********** ********** **********
Retained Earnings (%Age) ********** ********** ********** ********** **********
Book Value Per Share (in `) ********** ********** ********** ********** **********
Debt Per Share (in `) ********** ********** ********** ********** **********
Probable Mkt.Price/Share(in `) ********** ********** ********** ********** **********
Price / Book Value (x) ********** ********** ********** ********** **********
Price Earnings Ratio (x) ********** ********** ********** ********** **********
Yield (%Age) ********** ********** ********** ********** **********

BREAK EVEN ANALYSIS

Particulars Operating Years
Ratio 1-2 2-3 3-4 4-5 5-6
BREAK EVEN ANALYSIS
Total Value of Output ********** ********** ********** ********** **********
Variable Cost & Expenses
Raw Material Cost ********** ********** ********** ********** ********** **********
Lab & ETP Chemical Cost ********** ********** ********** ********** ********** **********
Packing Material Cost ********** ********** ********** ********** ********** **********
Sales Commission/Exp. ********** ********** ********** ********** ********** **********
Sub-total ********** ********** ********** ********** **********
Less:W.I.P. Adjustments ********** ********** ********** ********** **********
Total Variable Cost ********** ********** ********** ********** **********
Net Contribution ********** ********** ********** ********** **********
Profit Volume Ratio (%) ********** ********** ********** ********** **********
Semi-Var./Semi-Fixed Exp.
Miscellaneous Cost ********** ********** ********** ********** ********** **********
Employees Expenses ********** ********** ********** ********** ********** **********
Power/Electricity Expen ********** ********** ********** ********** ********** **********
Fuel Expenses ********** ********** ********** ********** ********** **********
Royalty & Other Charges ********** ********** ********** ********** ********** **********
Repairs & Maintenance E ********** ********** ********** ********** ********** **********
Other Mfg. Expenses ********** ********** ********** ********** ********** **********
Administration Expenses ********** ********** ********** ********** ********** **********
Selling Expenses ********** ********** ********** ********** ********** **********
Interest on Wkg.Capital ********** ********** ********** ********** ********** **********
Tot.Semi-Var./Fixed Exp. ********** ********** ********** ********** **********
**********
Fixed Expenses / Cost **********
Miscellaneous Cost ********** ********** ********** ********** ********** **********
Employees Expenses ********** ********** ********** ********** ********** **********
Power/Electricity Expen ********** ********** ********** ********** ********** **********
Fuel Expenses ********** ********** ********** ********** ********** **********
Royalty & Other Charges ********** ********** ********** ********** ********** **********
Repairs & Maintenance E ********** ********** ********** ********** ********** **********
Other Mfg. Expenses ********** ********** ********** ********** ********** **********
Administration Expenses ********** ********** ********** ********** ********** **********
Selling Expenses ********** ********** ********** ********** ********** **********
Intrest-Fixed Borrowing ********** ********** ********** ********** ********** **********
Intrest-Working Capital ********** ********** ********** ********** ********** **********
Depreciation Charges ********** ********** ********** ********** ********** **********
Deferred Expenses W/Off ********** ********** ********** ********** ********** **********
Total Fixed Expenses ********** ********** ********** ********** **********
Tot.Fixed/Semi-Fixed Exp ********** ********** ********** ********** **********
Tot.Cash Fixed/SemiFixed ********** ********** ********** ********** **********
Cash Break Even Sales ********** ********** ********** ********** **********
Cash Margin of Safety ********** ********** ********** ********** **********
Break Even Sales ********** ********** ********** ********** **********
Margin of safety ********** ********** ********** ********** **********
At Maximum Utilisation : Year ********** ********** ********** ********** **********
(as % of Installed Capacity)
Cash B.E.P. : % xx% xx% xx% xx% xx%
B.E.P. : % xx% xx% xx% xx% xx%

MEANS OF FINANCE

Equity Share Capital ********** ********** **********
Others - Preference Share Capital ********** ********** **********
Total Equity Share Capital ********** ********** **********
********** ********** **********
Long/Medium Term Borrowings ********** ********** **********
FROM BANK ********** ********** **********
From Other Financial Institutions ********** ********** **********
Total Long/Medium Term Borrowings ********** ********** **********
********** ********** **********
Total Means of Finance ********** ********** **********

INTEREST AND REPAYMENT ON TERM LOANS

A Name of Institution-Bank ABC BANK
B Term Borrowing Amount ********** xx
C Repayment Term (Years) ********** Years
D Repayment Instalments ********** Instalments
E Repayment Commencement Year - 0; 3rd Qtr.
F Rate of Interest(General) xxxx% p.a.
F Rate of Interest(Initial) 0.00% p.a.
G Apply Gen. Int. Rate from Year x Quarter :: x
H Interest Calculation Quarterly

Debt Service Coverage Ratio

Funds Available to Service Debts
Net Profit After Taxes ********** ********** ********** ********** **********
Depreciation Charges ********** ********** ********** ********** **********
Technical Knowhow Fees & Expenses ********** ********** ********** ********** **********
Interest on Long/Medium Term ********** ********** ********** ********** **********
T o t a l ********** ********** ********** ********** **********
Debt Service Obligations ********** ********** ********** ********** **********
Repayment of Long/Medium Term ********** ********** ********** ********** **********
Interest on Long/Medium Term ********** ********** ********** ********** **********
T o t a l ********** ********** ********** ********** **********
********** ********** ********** ********** **********
D. S. C. R. (Individual) ********** ********** ********** ********** **********
D. S. C. R. (Cumulative) ..... ********** ********** ********** ********** **********
D. S. C. R. (Overall) ........ ********** ********** ********** ********** **********

DEPRECIATION CHARGES AS PER BOOKS (TOTAL)

Operating Year F.Assets Type A-1 F.Assets Type A-2 F.Assets Type B F.Assets Type C F.Assets Type D-1 F.Assets Type D-2 Total
Particulars Factory Building - Office Buildings PLANT & MACHINERY Office Vehicles Office Automation Equipments (Telephone/ Fax/ Computer) Furniture & Fixtures
1-2 ********** ********** ********** ********** ********** ********** **********
2-3 ********** ********** ********** ********** ********** ********** **********
3-4 ********** ********** ********** ********** ********** ********** **********
4-5 ********** ********** ********** ********** ********** ********** **********
5-6 ********** ********** ********** ********** ********** ********** **********
Particulars Method Deprn.Rate Part Consideration (for Asset put to use less than xx months)
Type A :: Buildings
Factory Building - WDV ********** **********
Office Buildings WDV ********** **********
Type C
Office Vehicles WDV ********** **********
Type D :: Misc. Fixed Assets
Office Automation Equipments (Telephone/ Fax/ Computer) WDV ********** **********
Furniture & Fixtures WDV ********** **********

Projected Pay Back Period

Particulars Operating Years
1-2 2-3 3-4 4-5 5-6
Year 1 2 3 4 5
Initial Investment *********
Total Initial Investment *********
Yearly Cash Flow ********* ********* ********* ********* *********
Accumulated Cash Flow ********* ********* ********* ********* *********
Pay Back Period xx Years xx Months xx Years xx months

Projected IRR

Year CFAT PV factor @**% *********
Initial Investment ********* ********* *********
1-2 ********* ********* *********
2-3 ********* ********* *********
3-4 ********* ********* *********
4-5 ********* ********* *********
5-6 ********* ********* *********
Total PV ********* *********
IRR ********* *********

PROJECTED BALANCE SHEET

Particulars Operating Years
1-2 2-3 3-4 4-5 5-6
Equity Share Capital ********** ********** ********** ********** **********
Surplus of Previous Year ********** ********** ********** ********** **********
Add : Net Profit After Taxes ********** ********** ********** ********** **********
Surplus at the End of Year ********** ********** ********** ********** **********
Unsecured Deposits ********** ********** ********** ********** **********
Long/Medium Term Borrowings Proposed-FROM BANK ********** ********** ********** ********** **********
Bank Borrowing for Wkg. Capital ********** ********** ********** ********** **********
Current Liabilities ********** ********** ********** ********** **********
Sundry Creditors ********** ********** ********** ********** **********
Other Current Liabilities ********** ********** ********** ********** **********
Total Current Liabilities ********** ********** ********** ********** **********
********** ********** ********** ********** **********
Total of Liabilities ********** ********** ********** ********** **********
********** ********** ********** ********** **********
A S S E T S ********** ********** ********** ********** **********
Fixed Assets ********** ********** ********** ********** **********
Gross Block ********** ********** ********** ********** **********
Less : Depreciation to Date ********** ********** ********** ********** **********
Net Block ********** ********** ********** ********** **********
Current Assets ********** ********** ********** ********** **********
Stocks on Hand ********** ********** ********** ********** **********
Receivables ********** ********** ********** ********** **********
Other Current Assets ********** ********** ********** ********** **********
Cash and Bank Balances ********** ********** ********** ********** **********
Total Current Assets ********** ********** ********** ********** **********
P & P Exp. and/or Other Dvp.Exp. ********** ********** ********** ********** **********
(To The Extent Not W/Off) ********** ********** ********** ********** **********
Other Non Current Assets ********** ********** ********** ********** **********
********** ********** ********** ********** **********
Total of Assets ********** ********** ********** ********** **********
********** ********** ********** ********** **********
ROI (Average of Fixed Assets) ********** ********** ********** ********** **********
RONW (Average of Share Capital) ********** ********** ********** ********** **********
ROI (Average of Total Assets) ********** ********** ********** ********** **********

COMPANY SUMMARY

NIIR PROJECT CONSULTANCY SERVICES (NPCS)is a reliable name in the industrial world for offering integrated technical consultancy services. NPCS is manned by engineers, planners, specialists, financial experts, economic analysts and design specialists with extensive experience in the related industries.

Our various services are: Detailed Project Report, Business Plan for Manufacturing Plant, Start-up Ideas, Business Ideas for Entrepreneurs, Start up Business Opportunities, entrepreneurship projects, Successful Business Plan, Industry Trends, Market Research, Manufacturing Process, Machinery, Raw Materials, project report, Cost and Revenue, Pre-feasibility study for Profitable Manufacturing Business, Project Identification, Project Feasibility and Market Study, Identification of Profitable Industrial Project Opportunities, Business Opportunities, Investment Opportunities for Most Profitable Business in India, Manufacturing Business Ideas, Preparation of Project Profile, Pre-Investment and Pre-Feasibility Study, Market Research Study, Preparation of Techno-Economic Feasibility Report, Identification and Selection of Plant, Process, Equipment, General Guidance, Startup Help, Technical and Commercial Counseling for setting up new industrial project and Most Profitable Small Scale Business.

NPCS also publishes varies process technology, technical, reference, self employment and startup books, directory, business and industry database, bankable detailed project report, market research report on various industries, small scale industry and profit making business. Besides being used by manufacturers, industrialists and entrepreneurs, our publications are also used by professionals including project engineers, information services bureau, consultants and project consultancy firms as one of the input in their research.

REASONS FOR BUYING THE REPORT

  1. This report helps you to identify a profitable project for investing or diversifying into by throwing light to crucial areas like industry size, demand of the product and reasons for investing in the product.
  2. This report provides vital information on the product like its definition, characteristics and segmentation.
  3. This report helps you market and place the product correctly by identifying the target customer group of the product.
  4. This report helps you understand the viability of the project by disclosing details like raw materials required, manufacturing process, project costs and snapshot of other project financials.
  5. The report provides forecasts of key parameters which helps to anticipate the industry performance and make sound business decision.

OUR APPROACH

  1. Our research reports broadly cover Indian markets, present analysis, outlook and forecast.
  2. The market forecasts are developed on the basis of secondary research and are cross-validated through interactions with the industry players.
  3. We use reliable sources of information and databases. And information from such sources is processed by us and included in the report.

TABLE OF CONTENT

Introduction
Project Introduction
Project Objective and Strategy
Concise History of the Product
Properties
BIS (Bureau of Indian Standards) Provision & Specification
Uses & Applications

Market Study and Assessment
Current Indian Market Scenario
Present Market Demand and Supply
Estimated Future Market Demand and Forecast
Statistics of Import & Export
Names & Addresses of Existing Units (Present Players)
Market Opportunity

Raw Material
List of Raw Materials
Properties of Raw Materials
Prescribed Quality of Raw Materials
List of Suppliers and Manufacturers

Personnel (Manpower) Requirements
Requirement of Staff & Labor (Skilled and Unskilled) Managerial, Technical, Office Staff and Marketing Personnel

Plant and Machinery
List of Plant & Machinery
Miscellaneous Items
Appliances & Equipments
Laboratory Equipments & Accessories
Electrification
Electric Load & Water
Maintenance Cost
Sources of Plant & Machinery (Suppliers and Manufacturers)

Manufacturing Process and Formulations
Detailed Process of Manufacture with Formulation
Packaging Required
Process Flow Sheet Diagram

Infrastructure and Utilities
Project Location
Requirement of Land Area
Rates of the Land
Built Up Area
Construction Schedule
Plant Layout and Requirement of Utilities

FINANCIAL PLAN

Assumptions for Profitability workings Plant Economics
Production Schedule
Land & Building
  • Factory Land & Building
  • Site Development Expenses
Plant & Machinery
  • Indigenous Machineries
  • Other Machineries (Miscellaneous, Laboratory etc.)
Other Fixed Assets
  • Furniture & Fixtures
  • Pre-operative and Preliminary Expenses
  • Technical Knowhow
  • Provision of Contingencies
Working Capital Requirement Per Month
  • Raw Material
  • Packing Material
  • Lab & ETP Chemical Cost
  • Consumable Store
Overheads Required Per Month And Per Annum
  • Utilities & Overheads (Power, Water and Fuel Expenses etc.)
  • Royalty and Other Charges
  • Selling and Distribution Expenses
Salary and Wages
Turnover Per Annum
Share Capital
  • Equity Capital
  • Preference Share Capital
Annexure 1:: Cost of Project and Means of Finance
Annexure 2:: Profitability and Net Cash Accruals
  • Revenue/Income/Realisation
  • Expenses/Cost of Products/Services/Items
  • Gross Profit
  • Financial Charges
  • Total Cost of Sales
  • Net Profit After Taxes
  • Net Cash Accruals
Annexure 3 :: Assessment of Working Capital requirements
  • Current Assets
  • Gross Working. Capital
  • Current Liabilities
  • Net Working Capital
  • Working Note for Calculation of Work-in-process
Annexure 4 :: Sources and Disposition of Funds
Annexure 5 :: Projected Balance Sheets
  • ROI (Average of Fixed Assets)
  • RONW (Average of Share Capital)
  • ROI (Average of Total Assets)
Annexure 6 :: Profitability ratios
  • D.S.C.R
  • Earnings Per Share (EPS)
  • Debt Equity Ratio
Annexure 7 :: Break-Even Analysis
  • Variable Cost & Expenses
  • Semi-Var./Semi-Fixed Exp.
  • Profit Volume Ratio (PVR)
  • Fixed Expenses / Cost
  • B.E.P
Annexure 8 to 11:: Sensitivity Analysis-Price/Volume
  • Resultant N.P.B.T
  • Resultant D.S.C.R
  • Resultant PV Ratio
  • Resultant DER
  • Resultant ROI
  • Resultant BEP
Annexure 12 :: Shareholding Pattern and Stake Status
  • Equity Capital
  • Preference Share Capital
Annexure 13 :: Quantitative Details-Output/Sales/Stocks
  • Determined Capacity P.A of Products/Services
  • Achievable Efficiency/Yield % of Products/Services/Items
  • Net Usable Load/Capacity of Products/Services/Items
  • Expected Sales/ Revenue/ Income of Products/ Services/ Items
Annexure 14 :: Product wise domestic Sales Realisation Annexure 15 :: Total Raw Material Cost
Annexure 16 :: Raw Material Cost per unit Annexure 17 :: Total Lab & ETP Chemical Cost
Annexure 18 :: Consumables, Store etc., Annexure 19 :: Packing Material Cost
Annexure 20 :: Packing Material Cost Per Unit Annexure 21 :: Employees Expenses
Annexure 22 :: Fuel Expenses Annexure 23 :: Power/Electricity Expenses
Annexure 24 :: Royalty & Other Charges Annexure 25 :: Repairs & Maintenance Exp.
Annexure 26 :: Other Mfg. Expenses Annexure 27 :: Administration Expenses
Annexure 28 :: Selling Expenses Annexure 29 :: Depreciation Charges – as per Books (Total)
Annexure 30 :: Depreciation Charges – as per Books (P & M) Annexure 31 :: Depreciation Charges - As per IT Act WDV (Total)
Annexure 32 :: Depreciation Charges - As per IT Act WDV (P & M) Annexure 33 :: Interest and Repayment - Term Loans
Annexure 34 :: Tax on Profits Annexure 35 ::Projected Pay-Back Period And IRR

INFORMATION/ DISCLAIMER

  • One Lac / Lakh / Lakhs is equivalent to one hundred thousand (100,000)
  • One Crore is equivalent to ten million (10,000,000)
  • T.C.I is Total Capital Investment
  • We can modify the project capacity and project cost as per your requirement.
  • We can also prepare project report on any subject as per your requirement.
  • Caution: >The project's cost, capacity and return are subject to change without any notice. Future projects may have different values of project cost, capacity or return.