The first group includes the following main resources:
Entrepreneurs can target high-potential sectors that align with Karnataka’s competitive advantages:
However, Karnataka typically provides the sectoral and region-specific facilitations as follows:
- Single-window clearance and industry facilitation agencies for approvals, land allotment;
- sectoral incentives (electronics, biotech, aerospace, EVs) like capital subsidies, interest reimbursement, GST/tax concessions in approved cases;
- industrial land and plug-and-play facilities via state industrial development authorities, and private industrial parks;
- R&D and incubation grants, testing labs, and skill-development partnerships to speed up tech commercialization.
That long innovation velocity of a leading global tech center mature, though mature manufacturing clusters and heartland rural agricultural zones like us.
A competitive advantage that is virtually a hybrid one which would involve both the intensive start-ups of knowledge as well as manufacturing/processing projects. Additionally and beside the above, there is technology, biotechnology, aerospace, electronics, green power, and agro-value addition as far as either of which go, some scaling options and supportive public-private even for those at the level of angel investors and keyword the entrepreneur ventures that are already favored.
Please choose a project below related to this category.
The Indian pharmaceutical sector has come a long way, being almost non-existent before 1970 to a prominent provider of healthcare products, meeting al...
|
Capacity : Tablets:10,000 Strips/Day •Capsules:10,000 Strips/Day |
Plant and Machinery cost: Rs 262 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 28.00 |
|
Break Even Point (BEP): 54.00 |
TCI : Cost of Project:Rs 554 Lakhs |
|
Cost of Project : 55400000 |
A medical college is meant to impart education of medical field to students to qualify them as doctors in different specialized disciplines so as to t...
|
Capacity : Total Students per Annum:150 Students Admitted/Annum 750 Beded Hospital |
Plant and Machinery cost: Rs 2047 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 42.00 |
|
Break Even Point (BEP): 42.00 |
TCI : Cost of Project :Rs 10747 Lakhs |
|
Cost of Project : 1074700000 |
Detergents are defined as complete washing or cleaning products, which contain among their ingredients an organic surface-active compound (Surfactant)...
|
Capacity : 4MT/Day |
Plant and Machinery cost: Rs 18 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 26.00 |
|
Break Even Point (BEP): 43.00 |
TCI : Cost of Project:Rs 228 Lakhs |
|
Cost of Project : 22800000 |
PET, which stands for polyethylene terephthalate is a clear, strong and lightweight plastic belonging to the polyester family. It is typically called...
|
Capacity : PET Bottles/Jar 100 ml Size:16,000 Nos/Day •PET Bottles/Jar 200 ml Size:16,000 Nos/Day •PET Bottles/Jar 500 ml Size :16,000 Nos/Day •PET Bottles/Jar 1000 ml Size :16,000 Nos/Day •PET Bottles/Jar 2000 ml Size :16,000 Nos/Day |
Plant and Machinery cost: Rs 106 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 29.00 |
|
Break Even Point (BEP): 48.00 |
TCI : Cost of Project:Rs 546 Lakhs |
|
Cost of Project : 54600000 |
Apple is one of the delicious fruits. It contains vitamins, minerals, enzyme, fruit juices etc. It is very good taste to eat fresh and its juice also,...
|
Capacity : 800 Kgs/Day |
Plant and Machinery cost: Rs 336 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 26.00 |
|
Break Even Point (BEP): 41.00 |
TCI : Cost of Project:Rs 533 Lakhs |
|
Cost of Project : 53300000 |
Paper is a major product of the forestry industry, and is used widely in our society. Paper products are used not only in their obvious applications i...
|
Capacity : 100MT/Day |
Plant and Machinery cost: Rs 5457 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 26.62 |
|
Break Even Point (BEP): 54.00 |
TCI : Cost of Project:Rs 8300 Lakhs |
|
Cost of Project : 8300000 |
Egg is a highly nutritious product. Eggs are rich in protein, vitamins and minerals. The poultry sector has made tremendous progress in the last decad...
|
Capacity : 4.2MT/Day |
Plant and Machinery cost: Rs 672 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 26.00 |
|
Break Even Point (BEP): 49.00 |
TCI : Cost of Project:Rs 1044 Lakhs |
|
Cost of Project : 104400000 |
uPVC products are fire retardant. This is because they contain more than 70 % unplasticised uPVC which turns 57% Chlorine. This contribute efficiently...
|
Capacity : 8.3 MT/Day |
Plant and Machinery cost: Rs 161 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 26.00 |
|
Break Even Point (BEP): 41.00 |
TCI : Cost of Project:Rs 1119 Lakhs |
|
Cost of Project : 111900000 |
The betel nut (Supari) tree, which is known as "ARECA" in South India. It is planted in Bengal, Mysore, Sri Lanka etc. Its yield considered being very...
|
Capacity : Sweet & Scented Supari (2 gms Size Pouches) :20000 Pouches /Day •Sweet & Scented Supari (5 gms Size Pouches):8000 Pouches / Day •Sweet & Scented Supari (10 gms Size Pouches): 4000 Pouches / Day |
Plant and Machinery cost: Rs 9 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 27.00 |
|
Break Even Point (BEP): 68.00 |
TCI : Cost of Project :Rs 24 Lakhs |
|
Cost of Project : 2400000 |
A Multiplex is a multi screen entertainment complex showing different films under one roof with other type of supporting business in the vicinity like...
|
Capacity : 108 Seats Double Screen |
Plant and Machinery cost: Rs 157 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 21.24 |
|
Break Even Point (BEP): 57.13 |
TCI : Cost of Project:Rs 470 Lakhs |
|
Cost of Project : 47000000 |
Laundry detergent, or washing powder, is a type of detergent (cleaning agent) that is added for cleaning laundry. In common usage, "detergent" refers...
|
Capacity : Detergent Powder: 3.2 MT/Day •Liquid Washing Soap:3.2 MT/Day •Toilet Cleaner:3.2 MT/Day •Scouring Powder:3.2 MT/Day •Stain Remover Liquid:3.2 MT/Day |
Plant and Machinery cost: Rs 62 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 27.24 |
|
Break Even Point (BEP): 74.26 |
TCI : Cost of Project:Rs 185 Lakhs |
|
Cost of Project : 18500000 |
Spices are used for flavour, colour, aroma and preservation of food or beverages. Spices may be derived from many parts of the plant: bark, buds, flow...
|
Capacity : Chilli Oil :20 Kgs/Day •Chilli Oleoresin:60 Kgs/Day |
Plant and Machinery cost: Rs 57 Lakhs |
|
Working Capital : - |
Rate of Return (ROR): 27.91 |
|
Break Even Point (BEP): 59.00 |
TCI : Cost of Project: Rs 147 Lakhs |
|
Cost of Project : 14700000 |