Plaster of paris is a white hygroscopic powder having formula CaSo4? H2O is obtained by the calcination of gypsum. Plaster of paris is extensively use...
|
Capacity : 50 MT / Day 1500 MT / Annum |
Plant and Machinery cost: 47 Lakh |
|
Working Capital : - |
Rate of Return (ROR): 49.00 |
|
Break Even Point (BEP): 45.00 |
TCI : 3 Crores |
|
Cost of Project : 0 |
The use of granite and other decorative stones has been increasing world over. India is endowed with vast deposits of these natural resources and is t...
|
Capacity : 100 Sq. M./Day |
Plant and Machinery cost: Rs. 168 Lakhs |
|
Working Capital : Rs. 151 Lakhs |
Rate of Return (ROR): 47.73 |
|
Break Even Point (BEP): 42.87 |
TCI : Rs. 388 Lakhs |
|
Cost of Project : 0 |
Stabilizer are widely used to provide stabilized voltage to various items like Regrigerator, Television, Typewriter, and for various household purpose...
|
Capacity : 60 Nos./Day |
Plant and Machinery cost: Rs. 4 Lacs |
|
Working Capital : Rs. 9 Lacs |
Rate of Return (ROR): 64.82 |
|
Break Even Point (BEP): 40.62 |
TCI : Rs. 21 Lacs |
|
Cost of Project : 0 |
It is basically gum powder made from tamarind kernel, dimethyl hydantion formaldehyde, polyvinyl alcohol all the required raw material and machinery i...
|
Capacity : 1 MT/Day |
Plant and Machinery cost: - |
|
Working Capital : - |
Rate of Return (ROR): 27.23 |
|
Break Even Point (BEP): 52.93 |
TCI : - |
|
Cost of Project : 0 |
Cement is a very important building material. It is used in almost all the constructions and is subjected to water in contact. If the concrete or ceme...
|
Capacity : - |
Plant and Machinery cost: - |
|
Working Capital : - |
Rate of Return (ROR): 39.28 |
|
Break Even Point (BEP): 48.99 |
TCI : - |
|
Cost of Project : 0 |
Marble polishing batti is an essential item in the marble and granite polishing industries. Now a days there is good market demand of granite and marb...
|
Capacity : - |
Plant and Machinery cost: - |
|
Working Capital : - |
Rate of Return (ROR): 33.63 |
|
Break Even Point (BEP): 40.77 |
TCI : - |
|
Cost of Project : 0 |
Bricks may be made from a no. of different kinds of materials but they must usually posses a certain amount of plasticity. Fly ash is one of them. Fly...
|
Capacity : 250 Lacs Nos/Annum |
Plant and Machinery cost: Rs. 27.00 Lacs |
|
Working Capital : Rs. 62.0 Lacs |
Rate of Return (ROR): 27.16 |
|
Break Even Point (BEP): 65.69 |
TCI : Rs. 158.0 Lacs |
|
Cost of Project : 0 |
Admixtures are materials added to the concrete before or during its mixing, with a view to modifying one or more of the properties of concrete in the...
|
Capacity : 2000 Kgs/Day |
Plant and Machinery cost: 8 Lakhs |
|
Working Capital : 134 Lakhs |
Rate of Return (ROR): 52.00 |
|
Break Even Point (BEP): 41.00 |
TCI : 160 Lakhs |
|
Cost of Project : 0 |
With the vast potential of plastics, artificial synthetic marble is virtually replacing the use of natural marble. The qualities of artificial synthet...
|
Capacity : 3 MT/Day |
Plant and Machinery cost: Rs. 17 Lakhs |
|
Working Capital : Rs. 54 Lakhs |
Rate of Return (ROR): 43.00 |
|
Break Even Point (BEP): 49.00 |
TCI : Rs. 121 Lakhs |
|
Cost of Project : 0 |
The general outlook for the cement industry is fulfilled the situation in a large body of Indian Industry, with a market rise in production failing to...
|
Capacity : 50 MT/Day |
Plant and Machinery cost: Rs. 84 Lacs |
|
Working Capital : Rs. 74 Lacs |
Rate of Return (ROR): 23.00 |
|
Break Even Point (BEP): 63.00 |
TCI : Rs. 250 Lacs |
|
Cost of Project : 0 |
There are various uses of crushed stones, in rail road ballast, laying of roads, in concrete, plastering etc. The reduction of materials such as stone...
|
Capacity : 616 CUM/ Day |
Plant and Machinery cost: - |
|
Working Capital : - |
Rate of Return (ROR): 53.72 |
|
Break Even Point (BEP): 52.87 |
TCI : - |
|
Cost of Project : 0 |
Lime bonded fly ash bricks are the product of thermal power waste base products. There is no sophisticated machinery used in this production. There is...
|
Capacity : 20000 Nos. Bricks/Day |
Plant and Machinery cost: Rs. 12 Lakhs |
|
Working Capital : Rs. 1 Crore |
Rate of Return (ROR): 25.78 |
|
Break Even Point (BEP): 44.16 |
TCI : - |
|
Cost of Project : 0 |